Case Study:
Acoustek™ – Pipeline Blockage Detection

Acoustek™ – Pipeline Blockage Detection

iNPIPE PRODUCTS™ was approached to carry out a blockage detection survey on a 23,000m inland UK pipeline. The pipeline had recently been inspected using an inline inspection (ILI) tool; however, upon receipt, it was discovered that the ILI tool had broken one of its universal joints, and two trailing modules were left at an unknown location inside the pipeline. An Acoustek survey was requested to ascertain the module’s location, allowing them to perform an excavation to recover the modules.

Following a review of the project details & discussions with the Client, iNPIPE PRODUCTS™ provided a complete survey package consisting of:

  • Project management & documentation reviews
  • Supply & delivery of equipment
  • Supply of manpower
  • Analysis of recorded data

Locating the modules was critical to the continued operation of the pipeline, with location accuracy key to ensuring excavation work was performed only where required.

Three tie-in points were selected for the installation of the Acoustek gas gun, which were at the launch site, the receipt site, and at a branch 6,710m from the receipt site, connected to the pipeline via a tee. With the Acoustek survey providing data for up to 10,000m in a single direction, the confidence of detection from the three locations was high.

Acoustek shots were initially performed from the receipt end of the pipeline, as that was the suspected location of the modules following an assessment of pressure profiles during the ILI pig run. Further shots were performed via the branch and from the launch site. Shots from the receipt site identified a partial blockage at 728m from the tie-in point, with a further set of shots at elevated pressure supporting this. Shots were performed from the site connected to the pipeline via the tee, which showed two distinct responses at 6,710m and at 5,980m from the tie-in point. 6,710m is the known location of the receipt site, indicating that the modules are not fully blocking the pipeline. 5,980m is a location approximately 730m from the receipt site, which ties in well with the previous data set location for the modules. Data from the launch site provided no indication of a blockage within the acoustic range of the equipment, which was expected following the results from the other two locations.

The customer performed an excavation at the identified location, and the ILI modules were found and recovered. The pipeline was promptly repaired and returned to service.

       

Pigging Products and Services Association
BSi Logo
ISO9001 Quality Management certificate
ISO14001 Environmental Management Certificate
ISO45001 Health & Safety Management Certificate
North East England Chamber of Commerce
Constructionline Gold Member
SEQual member
European Desalination Society Member
International Desalination and Reuse Association (IDRA)
Avetta logo
EcoVadis Bronze Medal

Call +44 (0)1748 813270

© Copyright iNPIPE PRODUCTS™ 2026. All Rights Reserved.
International Pipeline Products Limited is registered in England and Wales, Company Number 01852899
Terms & Conditions | Privacy Policy